Home‎ > ‎

Boatshed Rebuild

 
Last updated
: Friday 14th August.

The History:
  
In 1935, the 1st Epping Scout Group started a Sea Scout section.  In 1939, the Group was fortunate to obtain a boatshed site at Meadowbank when AWA handed over their jetty, previously used for staff transport to the Homebush transmitter site.  The original shed was built with scrap timber under wartime rationing and opened in 1942, rebuilt in the 1950s, and later replaced with the brick structure shown here which opened in 1977 and included a rigging deck that used the concrete piers of the original building.  Although the Sea Scout section merged into the general Scout Troop in October 1984 the Group has continued running sailing and boating activities continuously to this day.
Extracted from the 1st Epping Scout Group Annual Report 1997.

The Project:
Around 2005, the Group Committee started putting money aside because they knew that the building was suffering from 25 years of the salt spray, the weather and more recently the effects from the ferries as they berthed at the nearby public ferry terminal.  At the end of 2015, the Group formed a committee to identify the projected requirements, design an affordable building that would hopefully meet the needs of the Group for the next 30 to 40 years and take the project to completion.  The new Boatshed floor will increase from 89m2 to 132m2 with an extension at the rear which leads to an L-shaped rigging deck.  The timber skid ramp is being replaced with a much safer gangway and floating pontoon to launch and retrieve the boats and canoes.  The floor and roof will be raised by 320 mm.  This is based on the recent and projected rise in sea levels (and a bit more), to maintain a dry floor.  The new roof will complement the roof design of the adjacent, recently completed Ferry Wharf.

After 4½ years of meetings with Ryde Council, Roads and Maritime Services (RMS), our architect, engineers and Scouts NSW, the construction is now ready to commence.    

Thanks to Brent and John Carolan from Skope Constructions for accepting the responsibility of providing the Epping Scout Group and Scouts NSW with a new facility that will enable the Scouts to experience sailing and canoeing in a safe and enjoyable environment well into the middle of the 21st century. 

The Construction:
30th April 2020 was the special day when the safety fencing was erected around the construction site.



5th May.  The doors have gone and the roof is coming off. 



6th May.  The signage has has gone up while the walls are starting to come down.  Today John Alexander, Federal MP for Bennelong and Jane Siebum, CEO for Scouts NSW, visited to check out the site and both were very pleased with the progress and that the construction was underway.  They were shown around by Brent and John Carolan from Skope Constructions.  Thanks to John Alexander for providing the Epping Scout Group with a $350,000 grant from the Federal Government in 2019 to assist with the construction.








8th May.  Only the Council toilet is left standing and the damaged concrete floor has been cut back so that the face can be sealed to prevent the ingress of water again.  The rigging deck has been removed to reveal the concrete piers that probably date back to the early 1940's.  The rigging deck that we have used for the last 40 years was previously the floor space of the original building.








12th May.  The rigging deck, skid ramp and their supports have been removed and put to rest.  The new piers will be protected by the plastic tubing that is visible on the slab.  The concrete steps are being removed.



14th May.  Some of the new plastic sleeves to hold the new piers.  This shows the size of the building extension and the width of the new rigging deck.




18th May.  The last of the plastic sleeves for the new piers are being secured prior to the sleeves being filled with concrete tomorrow.  This gives an idea of the increase in size.  The 9 taller piers at the right are for the building extension while the remaining ones are for the rigging deck.


19th May.  The sleeves are filled with concrete.  Each pier is secured with 3 stainless steel rods inserted 500mm into the rock shelf.


30th May.  As the weather has been very favourable over the last few weeks, progress has been ahead of schedule so there has not been any activity on site this week.  


4th June.  Preparation of the form work commenced on 1st June and will be continuing until the end of next week.  The new floor is scheduled to be poured on Friday 12th June.



9th June.  Not a lot of excitement while the formwork and reinforcing steel are set up for the new floor.



11th June.  Everything is ready for tomorrow's concrete pour.



12th June.  The slab was poured during light rain but everything went very well.  The green colouring is from the water proofing additive.

By Sunday it had mostly dried out.  Space for the 4.5m wide rigging deck to the right is not visible here.  The drains were covered during the pour.  The pooling of the remaining water is in the correct positions. 


17th June.  The blocks have arrived and 2 layers have been laid most of the way round.  It is too late to change the positions of the doors.

and by the next day the walls have been half built.


19th June.  Halfway up the wall has now been laid.  Formwork is being put in place to enable the blocks to be filled with concrete on Monday.  I would like to see the Big Bad Wolf try to blow this one down.



22nd June.  The concreters were back today to fill the lower half of the block walls.



24th June.  The bricklayers were back over the last 2 days to complete the top half of the walls.  The spaces for the doors and windows are now very obvious.



3rd July.  2 Months into the construction has provided us with a new set of foundations for the rigging deck, the concrete slab and the block walls completed and rendered.  Next stage will be the roof and rigging deck. 


6th July.  The exterior rendering is almost complete.  Still awaiting the final colour to be applied.   Note the adjacent Council toilet has been rendered to match.

9th July.
The formwork has now started to be laid to support the rigging deck.  The new L-shaped deck will provide us with an additional 6m x 10m rigging space.



17th July.  More of the rigging deck formwork has been completed at the rear of the building.  Away from the construction site,
the roof, wall and door colours have been discussed and nearly settled.  The picture below shows the proposed colours for the roof, walls and doors.   A lot of discussion and negotiation has been going on over the gangway and pontoon.  The 3m wide gangway will have a minimesh surface leading to the pontoon which will provide a flat 6m x 4m minimesh surface sitting 200mm above the waterline. 


 


24th July.  The driveway is prepared and ready for the concrete pour, scheduled for Monday morning.  Repairs to the sea wall underneath the building will be carried out soon to prevent any further erosion below the concrete slab.  Fabrication of the roof trusses has commenced so the roof will be coming soon.  The order for the gangway and pontoon has been placed.  It should take about 4 weeks to build these and they will be brought to the site ready to be installed.




29th July.  3 months into the construction, the concrete slab driveway was poured today after the previous 2 days were too wet.  It looks very impressive and will never need painting.


31st July.  The exterior walls have now been painted.


The view through the kitchen window.  


1st August.  I had lovely lunch with my wife, Judy, at the Fork and Spoon Cafe, this is the view of the boatshed.  It blends in very well with the surroundings.



11th Aug.  There has been no activity at the boatshed for just over a week but there will be lots of action coming soon.  The roof trusses are due to be delivered on Thursday and installed next week.   The roof and gables will be commenced soon after.  The big excitement will be the closer to the end of August when the pontoon and gangway are scheduled to be delivered and installed.


15th Aug.  The roof trusses have arrived but didn't justify a photo until the builder sent through some photos taken from their drone.



Comments